Project Description
Design and construct a sidewalk on Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard. Design and construct pedestrian signals at the intersection of Quesada Avenue and Forrest Nelson Boulevard.Project Location
North side of Quesada Avenue from Cochran Boulevard to Forrest Nelson Boulevard.Latest Updates
The bid package is assembled and we are just waiting on the SWFWMD exemption to be finalized then the package will be submitted to pruchasing to go out for bids for construction.Budget
Phase | Cost |
---|---|
Design | $133,681.00 |
Construction | $455,225.00 |
Total Budget | $588,906.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 03/31/2022 | 03/01/2023 |
Project Phase
Design Development
Last Updated
06/04/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c412104.41421
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD